Serian Roundabout -Pantu Junction (SPJ)

  • CH1+300 RHS- Removal of unsuitable material (Serian Section)
  • CH2+874- Bore piling works at Btg. Sadong (Serian Section)
  • CH2+874- Bore piling works at Btg. Sadong (Serian Section)
  • CH10+800 to CH14+800 LHS- Splicing of Telekom Malaysia fibre optic cable (Serian Section)
  • CH13+075 LHS- Spraying of shotcrete for slope stabilisation (Serian Section)
  • CH13+500 RHS- Earthwork cutting (Serian Section)
  • CH15+200 to CH15+800 RHS- Termination and energising of LT cable (Serian Section)
  • CH15+800 RHS- Removal of unsuitable material (Serian Section)
  • CH20+800- Laying of geotextile for ground treatment (Serian Section)
  • CH22+900 RHS- Earthwork cutting (Serian Section)
  • CH35+600 to CH36+675 LHS- Laying of geotextile and sand filling (Pantu Section)
  • CH47+555- Embankment fill (Pantu Section)
  • CH49+000- Trees cutting at Sabal Forest (Pantu Section)
  • CH59+397- Culvert works for Culvert B169 (Pantu Section)
  • CH70+100 RHS- Site clearing (Pantu Section)
Location Serian Roundabout to Pantu Junction
Scope Of Work Construction, Planning

Project Details

Serian Roundabout – Pantu Junction (SPJ)

WPC 03
Road Length:  75.015 km
Work will be carried out in 2 sections – Serian Section, Pantu Section
Interchanges: 3 (Serian 1, Serian 2, Simunjan)
Layby: 1 (Balai Ringin)
Bridges: 10
Bus Shelters: 84
Pedestrian Bridges: 8
Launched: March 2016
Contractor: ZECON KIMLUN Consortium Sdn. Bhd.