Sg. Kua Bridge – Sg. Arip Bridge (SKB)

  • CH 2+100_RC cascading drain completed
  • CH 6+800_Pier 2 Lean concrete in progress
  • CH 9+700_RC bench construction completed
  • CH 13+150_Cutting Slope work (5th bench)
  • CH 13+800 LHR_RE Wall Panel casting area for Selangau Interchange
  • CH 22+100 Sungai Sebaya Bridge_ Boring work for bored pile in progress
  • CH 34+455 LHS_Concreting work for wing wall and bottom haunch pipe culvert at CA88 in progress
  • CH 39+0000 LHS_Slope treatment with shotcrete method bench No.3 completed
  • CH 40+650 RHS_7nos of girder beam casting type 30 completed
  • CH 40+650 RHS_Conctering work for beam girder type 30 in progress
  • CH 41+400 RHS_Interceptor and bench drain completed on 1-3 slope completed
  • CH 45+400_Boring work for bore pile No. ABP2 in progress
  • CH 62+900_Pre-inspection for fabrication of rebar girder beam on going
  • CH55+840 LHS_Slope cutting work bench no 1-3 completed
  • Culvert CA 25_CH 7+219 RHS_Concreting for base slab
Location Sg. Kua Bridge to Sg. Arip (SKB)
Scope Of Work Construction, Planning

Project Details

WPC 08

Road Length:  63.678 km
Work will be carried out in 2 sections:  Selangau Section & Balingian Section
Interchanges: 1 (Selangau)
Rest & Service Area: 1 (Sg. Basai)Bridges: 14
Bus Shelters: 50
Pedestrian Bridges: 3
Contractor: Musyati Mudajaya JV Sdn. Bhd.