Sg. Awik Bridge – Bintangor Junction (SAB)

  • Bintangor Interchange - 1st tier RE wall and sand filling at abutment B CH63+900
  • Bkt Sebangkoi Sect - Culvert CH10+639
  • Bkt Sebangkoi Sect - Earthwork filling on top of ground treatment CH36+950
  • Bkt Sebangkoi Sect - Final subgrade preparation and median drain CH34+750 to CH35+000
  • Bkt Sebangkoi Sect - Laying of final roadbase CH5+900 to CH6+300
  • Bkt Sebangkoi Sect - Subgrade preparation and median drain CH17+600 to CH17+300
  • Bkt Sebangkoi Sect - Trial lay - 1st layer binder course CH0+000 to Ch0+150
  • Sarikei Flyover - Abutment A structure CH45+600
  • Sarikei Flyover - Installation of formwork and rebar for Abutment B cross head Ch45+675
  • Sarikei Sect - Earthwork (CH40+200 to 40+300)
  • Sg. Paoh Bridge - Pier 2 column in progress CH38+850
Location Sg. Awik to Bintangor Junction (SAB)
Scope Of Work Construction, Planning

Project Details

WPC 06

Road Length:  64.486 km
Work will be carried out in 2 sections: Bukit Sebangkoi Section & Sarikei Section
Interchanges: 2 (Sarikei, Bintangor)
Layby: 1 (Roban)

Bridges: 6
Bus Shelters: 59
Pedestrian Bridges: 5
Contractor: PPESW BPSB JV Sdn. Bhd.

Address: No 12A 1st Floor, Lorong Nenas 1, Jalan Nenas, 96100, Sarikei, Sarawak