Nyabau -Bakun Junction (NBJ)

  • Ch 6+500 increasing chainage
  • Ch 12+300 increasing chainage - Earthwork in progress at LHS
  • Ch 18+300 increasing chainage - Construction of second binder layer has completed at LHS
  • Ch 21+500 increasing chainage - Both side has completed till second layer ACBC 28 and LHS has open for traffic flow
  • Ch 29+200 increasing chainage - Both side has completed till second layer ACBC 28
  • Ch 42+000 increasing chainage - Both side has completed till second layer ACBC 28 and construction of shoulder at RHS
  • Figure 1 - Earth cut at Ch 19+300 LHS
  • Figure 2 - Earthcut at borrow pit area at Ch 34+600 RHS
  • Figure 3 - Compaction for median area at Ch 39+900
  • Figure 4 - Construction of roadshoulder at Ch 40+000 RHS
  • Figure 5 - Installation gabion wall at Ch 6+400 - 6+475 RHS a
  • Figure 6 - Preparing roadbase layer at Ch 6+625 - 6+970 LHS
  • Figure 7 - Preparing bottom subgrade at p turn area
  • Figure 8 - Trimming roadbase layer at Ch 18+200 LHS
  • Figure 9 - Compaction and preparing bottom subgrade layer at Ch 33+250 to 33+400 RHS
  • Figure 10 - Guardrail installation at Ch 41+000
  • Figure 11 - Backfilling abutment A
  • Figure 12 - Bridge 2A increasing chainage
  • Figure 13 - Bridge 3B decreasing chainage
  • Figure 14 - Embankment filling above pile head pier
  • Figure 15 - POB2 LHS-1
  • Figure 16 - Platform preparation for Culvert No.52 RHS
  • Figure 17 - Construction of french drain at Ch 42+600 LHS
  • Figure 18- Installation formwork and rebar for approach slab Culvert No.63 LHS
  • Figure 19 - Replanting Mucuna at CH 16+300 LHS
  • Figure 20 - Fertilizing Mucuna at CH 28+500 LHS
  • Figure 21 - Coring for Binder course layer at Ch 29+125 - 29+587 LHS
  • Figure 22 - Insitu CBR bottom subgrade layer at Ch 11+125 RHS
  • Figure 23 - Joint measurement for coring stonebase thickness at Ch 17+275 LHS
  • Figure 24 - Laying LT line at CH 1+200
  • Figure 25 - Installation DI pipe crossing at Ch 19+200
  • Figure 26 - Installation acc. for SESCO LT lines at Ch 2+550
Location Nyabau - Bakun Junction
Scope Of Work Construction, Planning
Schedule 2016 - 2023

Project Details

Pan Borneo Highway Sarawak’s Kick-Off Project

Road Length: 42.966 km
Bridges: 4
Bus Shelters: 26
Pedestrian Bridges: 2
Launched: March 2015
Contractor: Pekerjaan Piasau Konkerit Sdn. Bhd.