Nyabau -Bakun Junction (NBJ)

  • Boring bore pile pier 2 at BR3B in progress
  • CH3+245 to CH3+455 RHS- Pole erection for HT line
  • CH3+800 RHS- Excavation of hard material
  • CH6+325- Installation of pipe sleeve for underground cable
  • CH6+400 RHS- Cutting of earth material
  • CH6+750 RHS- Cutting of earth material
  • CH7+200 to CH7+300 LHS- Compaction at embankment fill
  • CH8+210 to CH8+260 LHS- Concreting of bench drain No.2
  • CH12+100 LHS- Slope trimming
  • CH17+100 to CH17+300 LHS- Preparation for subgrade level
  • CH18+250 to CH18+753- Laying of 50mm DCR for top subgrade layer
  • CH36+100 LHS- Laying of DCR 38mm for subbase layer
  • CH36+490 to CH36+650 RHS- Concreting of base slab for RSD
  • CH41+600 LHS- Laying of 1st binder layer
  • Installation of pipe culvert at Culvert 30
  • Piling for 150mmx150mm RC SQ pile at culvert No.28
  • Stressing work for girder beam 117.25m
  • View of BR1B taken from abutment A increasing chainage
  • View of BR2B ready to open for traffic flow
Location Nyabau - Bakun Junction
Scope Of Work Construction, Planning
Schedule 2016 - 2023

Project Details

Pan Borneo Highway Sarawak’s Kick-Off Project

Road Length: 42.966 km
Bridges: 4
Bus Shelters: 26
Pedestrian Bridges: 2
Launched: March 2015
Contractor: Pekerjaan Piasau Konkerit Sdn. Bhd.