Project Progress

PHASE 1 – TELOK MELANO TO MIRI

What’s Happening On Site – As At January 2018

As at January 2018, Pan Borneo Highway Sarawak is one-third into the construction period.

The main activities on the ground currently are earthwork, ground treatment, culverts, structural work and bridge and utilities Relocation works with most of the 11 works packages have started their road works i.e. subgrade, subbase or road base.

As for Telok Melano-Sematan (TMS) works package, it managed to execute its first ever trial lay in the middle of January this year, which is a big milestone as the construction works has gone into the core trade for road project – Pavement Works!