Powered by ZigaForm version 3.9.4.9

Happenings

LBU News

Road condition to improve as diversions reduced along Sg. Kua Bridge to Sg. Arip Bridge stretch

Wednesday, 18 December 2019, Selangau: The stretch along Sungai Kua Bridge to Sungai Arip Bridge (Works Package 08) will start to get better from now on for road users with less temporary diversions and more stretches to be diverted to permanent carriageway in stages.

While acknowledging the less than comfortable driving experience along this stretch, LBU project manager for WPC08, Baharuddin Samsuddin said these diversions were necessary for culvert replacement work to be carried out.

“From the day we started constructing this stretch, we are now seeing a sharp decrease, from the initial 153 to the current 89 diversions of which 64 diversions have already been completed and converted to the permanent carriageway.

“These diversions are necessary as the contractor has to replace the old culverts where we are talking about one for every 300m stretch. So, we have to create these diversions to allow for this replacement work to take place.

“Once each of these diversions is done, we will demolish it and divert the traffic to the permanent carriageway. The culvert work will then extend to the carriageway next to it but this second carriageway will not pose any hassle to road users as traffic is already shifted to the first carriageway,” he explained.

The remaining 89 diversions, he said, would all be demolished in stages and expected to be completed by mid of next year once the culvert work is entirely completed.

“By then, road users will not have to go through the hassle of travelling through these diversions as they will be shifted to the completed first carriageway, albeit up to the binder course layer,” he added.

Meanwhile, Baharuddin said 14km out of the 20km of carriageway in Selangau section, paved up to the binder course layer, had already been opened to traffic and more paving works would be continued.

“As for the Balingian section, the paving progress still continued and current 5km out of 7.8km, also paved up to binder course layer, are already opened to traffic,” he said.

Moving on to the Selangau Interchange, it is expected to be fully completed by March next year, with work focussing on its deck slabs and reinforced earth wall before moving to the subsequent road furniture.

The only interchange along the stretch, Selangau Interchange will smoothen the traffic for road users who travel from Mukah to Sibu and Bintulu and vice versa once it is completed.

This interchange also functions as an integration direction for the combination of road users either from Sibu, Mukah and Bintulu that will connect them through a new road stretch without disturbing the existing Selangau bazaar.

The main contractor for Works Package 08 is MMJV Sdn Bhd.